Discover a world of knowledge at Westonci.ca, where experts and enthusiasts come together to answer your questions. Join our Q&A platform and get accurate answers to all your questions from professionals across multiple disciplines. Get quick and reliable solutions to your questions from a community of experienced experts on our platform.

if 4 labourers can finish a job in 6days how long would it take 3men to do the job


Sagot :

Answer:

yes do have in an any job that occurred the an evrey one to know you.

Answer:

8 days

Step-by-step explanation:

no of men                                             no of days

4                                                                   6

3                                                                     let be x

there is indirect variation

4/3=6/x

since it is in indirect variation do the reciprocal of any one fraction among these two fractions

4/3=x/6

do cross multiplicatin

3*x=6*4

x=24/3

x=8

therefore it take 8 days to complete the same work by 3 men.

Thanks for stopping by. We strive to provide the best answers for all your questions. See you again soon. We appreciate your visit. Our platform is always here to offer accurate and reliable answers. Return anytime. Westonci.ca is committed to providing accurate answers. Come back soon for more trustworthy information.