Welcome to Westonci.ca, where you can find answers to all your questions from a community of experienced professionals. Experience the ease of finding accurate answers to your questions from a knowledgeable community of professionals. Our platform offers a seamless experience for finding reliable answers from a network of knowledgeable professionals.

if 4 labourers can finish a job in 6days how long would it take 3men to do the job


Sagot :

Answer:

yes do have in an any job that occurred the an evrey one to know you.

Answer:

8 days

Step-by-step explanation:

no of men                                             no of days

4                                                                   6

3                                                                     let be x

there is indirect variation

4/3=6/x

since it is in indirect variation do the reciprocal of any one fraction among these two fractions

4/3=x/6

do cross multiplicatin

3*x=6*4

x=24/3

x=8

therefore it take 8 days to complete the same work by 3 men.

We hope you found what you were looking for. Feel free to revisit us for more answers and updated information. Thank you for your visit. We're dedicated to helping you find the information you need, whenever you need it. Stay curious and keep coming back to Westonci.ca for answers to all your burning questions.