Westonci.ca offers quick and accurate answers to your questions. Join our community and get the insights you need today. Explore comprehensive solutions to your questions from a wide range of professionals on our user-friendly platform. Get quick and reliable solutions to your questions from a community of experienced experts on our platform.
Sagot :
Answer:
a) Minimize Z =30 X1 +25 X2+18 X3
subject to following constraints
[tex]1.X1\geq 0.4\left ( X1+X2 \right )\\2.X3\geq 0.15\left ( X1+X2+X3 \right )\\3.X1+X2+X3\leq 150\\4.X3\geq 0.25\left ( X1+X2 \right )\\5.X1\leq 50\\6.X1,X2,X3\geq 0[/tex]
b) Total cost=[tex]30 \times 48+15\times72+18\times30[/tex] = $3180.
c) As the dual price for constraint five is zero hence additional work hours for Lisa won't change the optimum solution.
Step-by-step explanation:
Step 1:-
a)
Let's take
X1 to be the number of hours assigned to Lisa
X2 to be the number of hours assigned to David
X3 to be the number of hours assigned to Sarah.
The objective function is to attenuate the entire cost of the project by deciding an optimum number of hours for every person. the target function is given by -
Minimize Z =30 X1 +25 X2+18 X3
subject to following constraints
[tex]1.X1\geq 0.4\left ( X1+X2 \right )\\2.X3\geq 0.15\left ( X1+X2+X3 \right )\\3.X1+X2+X3\leq 150\\4.X3\geq 0.25\left ( X1+X2 \right )\\5.X1\leq 50\\6.X1,X2,X3\geq 0[/tex]
Constraints and explanation:
1. Lisa must be assigned a minimum of 40% of the entire number of hours assigned to the 2 senior designers.
2. Sarah must be assigned a minimum of 15% of the entire project time.
3. The corporate estimates that 150 hours are going to be required to finish the project.
4. The number of hours assigned to Sarah must not exceed 25% of the entire number of hours assigned to the 2 senior designers.
5. Lisa features a maximum of fifty hours available to figure on this project.
6. Non-negative condition.
Step 2:-
b)
From the above equations, we get
The number of hours assigned to Lisa is 48 hours
The number of hours assigned to David 72 hours
The number of hours assigned to Sarah 30 hours.
Total cost=[tex]30 \times 48+15\times72+18\times30[/tex] = $3180.
Step 3:-
c)
As the dual price for constraint five is zero hence additional work hours for Lisa won't change the optimum solution.
We appreciate your time on our site. Don't hesitate to return whenever you have more questions or need further clarification. We hope you found this helpful. Feel free to come back anytime for more accurate answers and updated information. We're glad you visited Westonci.ca. Return anytime for updated answers from our knowledgeable team.