Discover the answers you need at Westonci.ca, where experts provide clear and concise information on various topics. Connect with professionals ready to provide precise answers to your questions on our comprehensive Q&A platform. Connect with a community of professionals ready to help you find accurate solutions to your questions quickly and efficiently.

An order for 140 units of Product A has been placed. There are currently 20 units of Product A on hand. Each Product A requires 3 units of Component B. There are 40 units of Component B on hand. What are the net requirements for Component B

Sagot :

Answer:

Order for unit B = 440

Explanation:

Given:

Order for unit A = 140 units

Units A in hand = 20 units

Units B in hand = 40 units

1 unit A required 3 units of B

Find:

Order for unit B

Computation:

Total unit of A = 140 + 20

Total unit of A = 160 units

Total unit B required = 160 x 3

Total unit B required = 480

Order for unit B = Total unit B required - Units B in hand

Order for unit B = 480 - 40

Order for unit B = 440