At Westonci.ca, we connect you with experts who provide detailed answers to your most pressing questions. Start exploring now! Connect with professionals on our platform to receive accurate answers to your questions quickly and efficiently. Get immediate and reliable solutions to your questions from a community of experienced professionals on our platform.

14.With earned value management (EVM), the Government can determine if a program is currently experiencing a/n

Sagot :

Answer: cost or schedule variance

Explanation:

Earned value management, refers to the project management technique that's used for the measurement of project progress and performance.

Earned value management integrates the cost, schedule, and scope in the measurement of project performance and this can be used by the government to determine if a program is currently experiencing a cost or schedule variance.