At Westonci.ca, we make it easy for you to get the answers you need from a community of knowledgeable individuals. Get detailed and accurate answers to your questions from a community of experts on our comprehensive Q&A platform. Get detailed and accurate answers to your questions from a dedicated community of experts on our Q&A platform.
Sagot :
Answer:
Variable cost per unit= $8.4
Explanation:
First, we need to calculate the total cost for each level of machine hours:
Low activity level:
Total cost= 22,000*33.4= $734,800
High activity level:
Total cost= 25,000*30.4= $760,000
Now, we can determine the variable and fixed costs:
Variable cost per unit= (Highest activity cost - Lowest activity cost)/ (Highest activity units - Lowest activity units)
Variable cost per unit= (760,000 - 734,800) / (25,000 - 22,000)
Variable cost per unit= $8.4
Fixed costs= Highest activity cost - (Variable cost per unit * HAU)
Fixed costs= 760,000 - (8.4*25,000)
Fixed costs= $550,000
Fixed costs= LAC - (Variable cost per unit* LAU)
Fixed costs= 734,800 - (8.4*22,000)
Fixed costs= $550,000
Thank you for your visit. We're dedicated to helping you find the information you need, whenever you need it. We hope this was helpful. Please come back whenever you need more information or answers to your queries. Discover more at Westonci.ca. Return for the latest expert answers and updates on various topics.