Welcome to Westonci.ca, where curiosity meets expertise. Ask any question and receive fast, accurate answers from our knowledgeable community. Get detailed and precise answers to your questions from a dedicated community of experts on our Q&A platform. Get quick and reliable solutions to your questions from a community of experienced experts on our platform.
Sagot :
Answer:
Variable cost per unit= $8.4
Explanation:
First, we need to calculate the total cost for each level of machine hours:
Low activity level:
Total cost= 22,000*33.4= $734,800
High activity level:
Total cost= 25,000*30.4= $760,000
Now, we can determine the variable and fixed costs:
Variable cost per unit= (Highest activity cost - Lowest activity cost)/ (Highest activity units - Lowest activity units)
Variable cost per unit= (760,000 - 734,800) / (25,000 - 22,000)
Variable cost per unit= $8.4
Fixed costs= Highest activity cost - (Variable cost per unit * HAU)
Fixed costs= 760,000 - (8.4*25,000)
Fixed costs= $550,000
Fixed costs= LAC - (Variable cost per unit* LAU)
Fixed costs= 734,800 - (8.4*22,000)
Fixed costs= $550,000
Thank you for your visit. We are dedicated to helping you find the information you need, whenever you need it. We hope you found what you were looking for. Feel free to revisit us for more answers and updated information. Thank you for using Westonci.ca. Come back for more in-depth answers to all your queries.