Discover a world of knowledge at Westonci.ca, where experts and enthusiasts come together to answer your questions. Our Q&A platform provides quick and trustworthy answers to your questions from experienced professionals in different areas of expertise. Experience the convenience of finding accurate answers to your questions from knowledgeable experts on our platform.

How long will it take the same crew to clear the entire plot of 2 1/2 acres?

How Long Will It Take The Same Crew To Clear The Entire Plot Of 2 12 Acres class=

Sagot :

Answer:

It will take 15 days for the same crew to clear the entire plot of 2 1/2 acres.

Step-by-step explanation:

Given that a crew clears brush from 1/3 acre of land in 2 days, to determine how long will it take the same crew to clear the entire plot of 2 1/2 acres, the following calculation must be performed:

1/3 = 0.333

1/2 = 0.5

0.333 = 2

2.5 = X

2.5 x 2 / 0.333 = X

15 = X

Therefore, it will take 15 days for the same crew to clear the entire plot of 2 1/2 acres.