Westonci.ca connects you with experts who provide insightful answers to your questions. Join us today and start learning! Our platform offers a seamless experience for finding reliable answers from a network of knowledgeable professionals. Our platform offers a seamless experience for finding reliable answers from a network of knowledgeable professionals.
Sagot :
Answer:
It will take 15 days for the same crew to clear the entire plot of 2 1/2 acres.
Step-by-step explanation:
Given that a crew clears brush from 1/3 acre of land in 2 days, to determine how long will it take the same crew to clear the entire plot of 2 1/2 acres, the following calculation must be performed:
1/3 = 0.333
1/2 = 0.5
0.333 = 2
2.5 = X
2.5 x 2 / 0.333 = X
15 = X
Therefore, it will take 15 days for the same crew to clear the entire plot of 2 1/2 acres.
We appreciate your time. Please revisit us for more reliable answers to any questions you may have. Thanks for using our platform. We aim to provide accurate and up-to-date answers to all your queries. Come back soon. We're glad you visited Westonci.ca. Return anytime for updated answers from our knowledgeable team.