At Westonci.ca, we make it easy for you to get the answers you need from a community of knowledgeable individuals. Get quick and reliable solutions to your questions from a community of seasoned experts on our user-friendly platform. Get immediate and reliable solutions to your questions from a community of experienced professionals on our platform.
Sagot :
Answer:
The Sureset Concrete Company
The tons of gravel and sand that should be purchased each day are:
Sand = 800 tons
Gravel = 700 tons
Step-by-step explanation:
Two ingredients for producing concrete = sand and gravel
Cost of sand per ton = $6
Cost of gravel per ton = $8
Sand and gravel = 75% of the concrete
Therefore 25% (100 - 75%) will be made up of cement and water
Tons of concrete produced each day = 2,000
Sand and gravel = 1,500 (2,000 * 75%)
Sand <= 40% of 2,000 = 800 tons
Gravel => 30% of 2,000 = 700 (1,500 - 800) tons
To minimize costs, 800 tons of gravel and 700 tons of sand should be purchased each day.
Total cost incurred daily for both sand and gravel = $10,400 (800 * $6 + 700 * $8)
We hope you found what you were looking for. Feel free to revisit us for more answers and updated information. Thank you for your visit. We're dedicated to helping you find the information you need, whenever you need it. Stay curious and keep coming back to Westonci.ca for answers to all your burning questions.