At Westonci.ca, we provide reliable answers to your questions from a community of experts. Start exploring today! Connect with a community of experts ready to help you find solutions to your questions quickly and accurately. Get precise and detailed answers to your questions from a knowledgeable community of experts on our Q&A platform.
Sagot :
Answer:
Albiston Corporation
Relevant and Irrelevant Costs:
Relevant Costs:
Alternative Q Alternative R
Power costs $36,600 $35,600
Inspection costs $32,000 $35,600
Irrelevant Costs:
Alternative Q Alternative R
Supplies costs $79,000 $79,000
Assembly costs $48,000 $48,000
Explanation:
a) Data and Comparisons:
Alternative Q Alternative R
Supplies costs $79,000 $79,000
Power costs $36,600 $35,600
Inspection costs $32,000 $35,600
Assembly costs $48,000 $48,000
b) Relevant costs make a difference in the choice between alternative Q or R. The costs that are the same in amount are not relevant. Supplies costs and Assembly costs are two irrelevant costs, while Power costs and Inspection costs are relevant because they are not the same under the two alternatives. They make a difference in the choice of each alternative.
We hope you found what you were looking for. Feel free to revisit us for more answers and updated information. We hope you found what you were looking for. Feel free to revisit us for more answers and updated information. Get the answers you need at Westonci.ca. Stay informed with our latest expert advice.