At Westonci.ca, we make it easy for you to get the answers you need from a community of knowledgeable individuals. Explore thousands of questions and answers from a knowledgeable community of experts ready to help you find solutions. Get immediate and reliable solutions to your questions from a community of experienced professionals on our platform.
Sagot :
Answer:
Albiston Corporation
Relevant and Irrelevant Costs:
Relevant Costs:
Alternative Q Alternative R
Power costs $36,600 $35,600
Inspection costs $32,000 $35,600
Irrelevant Costs:
Alternative Q Alternative R
Supplies costs $79,000 $79,000
Assembly costs $48,000 $48,000
Explanation:
a) Data and Comparisons:
Alternative Q Alternative R
Supplies costs $79,000 $79,000
Power costs $36,600 $35,600
Inspection costs $32,000 $35,600
Assembly costs $48,000 $48,000
b) Relevant costs make a difference in the choice between alternative Q or R. The costs that are the same in amount are not relevant. Supplies costs and Assembly costs are two irrelevant costs, while Power costs and Inspection costs are relevant because they are not the same under the two alternatives. They make a difference in the choice of each alternative.
Thank you for choosing our platform. We're dedicated to providing the best answers for all your questions. Visit us again. Thanks for using our platform. We aim to provide accurate and up-to-date answers to all your queries. Come back soon. Westonci.ca is here to provide the answers you seek. Return often for more expert solutions.