Westonci.ca is the best place to get answers to your questions, provided by a community of experienced and knowledgeable experts. Our Q&A platform provides quick and trustworthy answers to your questions from experienced professionals in different areas of expertise. Our platform provides a seamless experience for finding reliable answers from a network of experienced professionals.
Sagot :
Answer:
Critical path = A-D-F-H
Duration = 22
Explanation:
Given:
Activity A B C D E F G H
Time 5 3 7 6 7 3 10 8
The objective is to identify the critical path and to find the time needed to complete this project
Solution:
The possible paths are as follows,
A-C-H = 5+7+8 =20
A-D-F-H = 5+6+3+8 =22
A-D-G = 5+6+10 = 21
B-E-G = 3+7+10 = 20
B-E-F-H = 3+7+3+8 = 21
a)
Critical is the path with the longest duration
Critical path =A-D-F-H
The duration is 22
b)
The duration to complete the project is as follows,
Duration = Length of critical path = 22
We hope you found this helpful. Feel free to come back anytime for more accurate answers and updated information. Thank you for visiting. Our goal is to provide the most accurate answers for all your informational needs. Come back soon. Westonci.ca is your go-to source for reliable answers. Return soon for more expert insights.