At Westonci.ca, we provide clear, reliable answers to all your questions. Join our vibrant community and get the solutions you need. Experience the ease of finding precise answers to your questions from a knowledgeable community of experts. Discover in-depth answers to your questions from a wide network of professionals on our user-friendly Q&A platform.

Consider the following project network and activity times (in weeks): Activity A B C D E F G H Time 5 3 7 6 7 3 10 8 How much time will be needed to complete this project

Sagot :

Answer:

Please find the attached file of the complete question:

Explanation:

Please find the attached file of the solution:

Critical Path:  ACH

Duration: 21

Because C is on the Critical Path, it cannot be postponed without causing the project to be delayed.

E is not on the critical path, thus it may also be delayed by two weeks without causing the project to be delayed.

[tex]D : ES : 6, EF : 10, LS : 7, LF : 11[/tex]