Welcome to Westonci.ca, where your questions are met with accurate answers from a community of experts and enthusiasts. Our platform offers a seamless experience for finding reliable answers from a network of knowledgeable professionals. Explore comprehensive solutions to your questions from a wide range of professionals on our user-friendly platform.

hamilton construction company uses the percentage of completion method of accounting. in 2020. hamilton began work under

Sagot :

Question Completion:

Hamilton construction company uses the percentage of completion method of accounting.  In 2020, Hamilton began work on the construction of a hospital, which provides for a contract price of $2,195,000.  Other details follow: 202O 2021 Costs incurred during the year 637,600 1,000,000 Total estimated cost 1,594,000 1,637,600 Billings during the year 427,000 2,195,000 Collections during the year 343,000 1,509,000 What portion of the total contract price would be recognized as revenue in 2020?

Answer options: 2,195,000 878,000 1,097,500 427,000 343,000

Answer:

Hamilton Construction Company

The portion of the total contract price would be recognized as revenue in 2020 is:

= $878,000.

Explanation:

a) Data and Calculations:

Contract price = $2,195,000.

                                                          2020           2021

Costs incurred during the year $637,600  $1,000,000

Total estimated cost                  1,594,000     1,637,600

Billings during the year                427,000    2,195,000

Collections during the year         343,000    1,509,000

Percentage of completion= Cost incurred in 2020/Total estimated cost in 2020 * 100

= $637,600/$1,594,000  * 100

= 40%

Revenue to be recognized in 2020  = 40% * Contract Price

= $878,000 ($2,195,000 * 40%)