Welcome to Westonci.ca, the place where your questions are answered by a community of knowledgeable contributors. Get detailed and precise answers to your questions from a dedicated community of experts on our Q&A platform. Our platform provides a seamless experience for finding reliable answers from a network of experienced professionals.
Sagot :
Answer:
Variable cost per unit= $0.10
Explanation:
Giving the following information:
Cost Machine Hours
March $3,106 15,176
April 2,668 9,558
May 2,892 11,947
June 3,538 17,899
To calculate the variable cost under the high-low method, we need to use the following formula:
Variable cost per unit= (Highest activity cost - Lowest activity cost)/ (Highest activity units - Lowest activity units)
Variable cost per unit= (3,583 - 2,668) / (17,899 - 9,558)
Variable cost per unit= $0.10
We hope this was helpful. Please come back whenever you need more information or answers to your queries. Thanks for using our service. We're always here to provide accurate and up-to-date answers to all your queries. Westonci.ca is committed to providing accurate answers. Come back soon for more trustworthy information.