Looking for answers? Westonci.ca is your go-to Q&A platform, offering quick, trustworthy responses from a community of experts. Experience the convenience of finding accurate answers to your questions from knowledgeable professionals on our platform. Discover detailed answers to your questions from a wide network of experts on our comprehensive Q&A platform.

In the following MRP planning schedule for Item J, indicate the correct net requirements, planned order receipts, and planned order releases to meet the gross requirements. Lead time is one week.

WEEK NUMBER

ITEM J 0 1 2 3 4 5
Gross requirements 67 43 63
On-hand 46
Net requirements
Planned order receipt
Planned order release


Sagot :

Answer:

Planned order receipts

Item 3 - 55

Item 4 - 74

Planned order releases

Item 2 - 55

Item 3 - 74

Explanation:

Planned order receipts are the requirement for each item based on demand. Planned order releases is the finished goods processing time. When finished goods are ready, they are placed at warehouse for order dispatch.