Westonci.ca is your trusted source for finding answers to all your questions. Ask, explore, and learn with our expert community. Explore thousands of questions and answers from a knowledgeable community of experts on our user-friendly platform. Get quick and reliable solutions to your questions from a community of experienced experts on our platform.

Expando, Inc., is considering the possibility of building an additional factory that would produce a new addition to its product line. The company is currently considering two options. The first is a small facility that it could build at a cost of $7 million. If demand for new products is low, the company expects to receive $9 million in discounted revenues (present value of future revenues) with the small facility. On the other hand, if demand is high, it expects $14 million in discounted revenues using the small facility. The second option is to build a large factory at a cost of $8 million. Were demand to be low, the company would expect $9 million in discounted revenues with the large plant. If demand is high, the company estimates that the discounted revenues would be $13 million. In either case, the probability of demand being high is .30, and the probability of it being low is .70. Not constructing a new factory would result in no additional revenue being generated because the current factories cannot produce these new products.

1. Calculate the NPV for the following:

Plans NPV
Small facility $million
Do nothing million
Large facility million

2. The best decision to help Expando is:_________

Sagot :

Answer:

Expando, Inc.

1. NPV for the following:

Plans                 NPV

Small facility     $3.5 million

Do nothing         0 million

Large facility     2.2 million

2. The best decision to help Expando is:_________

to build a small facility.

Explanation:

a) Data and Calculations:

                                      Small Facility         Large Facility

Initial investment costs     $7 million            $8 million

Discounted revenues:

Low demand                       9 million              9 million

High demand                     14 million             13 million

Probability of low demand = 0.70

Probability of high demand = 0.30

Expected revenue              10.5 million         10.2 million

                    ($9m * 0.7 + $14m * 0.30)         ($9m * 0.7 + $13m * 0.30)

NPV                                     3.5 million           2.2 million

1. NPV for the following:

Plans                 NPV

Small facility     $3.5 million ($10.5 - $7) million

Do nothing         0 million ($0 - $0) million

Large facility     2.2 million ($10.2 - $8) million

Thank you for your visit. We are dedicated to helping you find the information you need, whenever you need it. Thanks for using our platform. We aim to provide accurate and up-to-date answers to all your queries. Come back soon. Find reliable answers at Westonci.ca. Visit us again for the latest updates and expert advice.