At Westonci.ca, we provide clear, reliable answers to all your questions. Join our vibrant community and get the solutions you need. Discover reliable solutions to your questions from a wide network of experts on our comprehensive Q&A platform. Connect with a community of professionals ready to provide precise solutions to your questions quickly and accurately.

Sheffield Corp. has a materials price standard of $2.00 per pound. 4900 pounds of materials were purchased at $2.20 a pound. The actual quantity of materials used was 4900 pounds, although the standard quantity allowed for the output was 4000 pounds. Sheffield Corp.'s materials quantity variance is:_____.
a. $1980 U.
b. $1800 F.
c. $1800 U.
d. $1980 F.

Sagot :

Answer:

a. $1,980 U

Explanation:

We will compute the direct materials quantity variance using the formula below.

Direct materials quantity variance =

(Standard quantity allowed - Actual quantity of materials) × Materials price standard

Fixing in the values, we'll have;

Direct materials quantity variance

= (4,000 pounds - 4,900 pounds) × $2.20 per pound

= -900 pounds × $2.20 per pound

= -$1,980

= $1,980 U

Thank you for your visit. We're dedicated to helping you find the information you need, whenever you need it. Thank you for your visit. We're committed to providing you with the best information available. Return anytime for more. Westonci.ca is here to provide the answers you seek. Return often for more expert solutions.