Welcome to Westonci.ca, the place where your questions find answers from a community of knowledgeable experts. Connect with professionals ready to provide precise answers to your questions on our comprehensive Q&A platform. Get immediate and reliable solutions to your questions from a community of experienced professionals on our platform.

1. A time study analyst timed an assembly operation for 30 cycles, and then computed the average time per cycle, which was 18.75 minutes. The analyst assigned a performance rating of .96, and decided that an appropriate allowance was 15%. Assume the allowance factor is based on the workday. Determine the following: observed time (OT), the normal time (NT), and the standard time (ST)

Sagot :

Answer:

1. observed time = 18.75 minutes.

2. Normal time = 18 minutes

3. Standard time = 21.17 minutes

Explanation:

1. The observed time will be equal to the average time per cycle, which was given in the question as 18.75 min. Therefore, observed time = 18.75 minutes.

2. The normal time will be:

= Average Time x Performance Rating

= 18.75 x 0.96

= 18 minutes

3. The standard time will be:

= Normal time × 1/(1 - 15%)

= Normal time × 1/(1 - 0.15)

= 18 × 1/0.85

= 18 × 1.176

= 21.17 minutes

Thanks for stopping by. We strive to provide the best answers for all your questions. See you again soon. Your visit means a lot to us. Don't hesitate to return for more reliable answers to any questions you may have. We're dedicated to helping you find the answers you need at Westonci.ca. Don't hesitate to return for more.