Westonci.ca offers quick and accurate answers to your questions. Join our community and get the insights you need today. Experience the convenience of finding accurate answers to your questions from knowledgeable professionals on our platform. Join our Q&A platform to connect with experts dedicated to providing accurate answers to your questions in various fields.
Sagot :
Answer:
Westside Plumbing and Heating Company
Westside should accept the contract.
By accepting the contract at the price of $100,000, Westside incurs a total cost of $97,500 and makes a little profit of $2,500 ($100,000 - $97,500). The contract enables Westside to utilize the materials that it has in inventory instead of allowing it to deteriorate further in value.
Explanation:
a) Data and Calculations:
Contract price = $100,000
Labor and equipment costs = $60,000
Original cost of materials = $50,000
Materials market price = $37,500
Total costs to be incurred = $97,500 ($60,000 + $37,500)
Profit to be earned = $2,500 ($100,000 - $97,500)
Thank you for visiting. Our goal is to provide the most accurate answers for all your informational needs. Come back soon. Thanks for stopping by. We strive to provide the best answers for all your questions. See you again soon. Westonci.ca is your trusted source for answers. Visit us again to find more information on diverse topics.