Welcome to Westonci.ca, your ultimate destination for finding answers to a wide range of questions from experts. Join our platform to connect with experts ready to provide accurate answers to your questions in various fields. Explore comprehensive solutions to your questions from knowledgeable professionals across various fields on our platform.

A firm uses a continuous review (Q) inventory system. Weekly demand for a product is normally distributed with a mean of 120 units and a standard deviation of 10 units. Lead time is constant at 4 weeks. The company reordered when 506 units of the product remained. About what cycle-service level (i.e., service level over the lead time) were they trying to maintain?

Sagot :

Answer: 90.32%

Explanation:

Weekly demand (d) = 120

Standard deviation = 10

Lead time (l) = 4

Reorder point = 506

The reorder point is calculated as:

506 = 120 × 4 + Z × 10 × ✓4

Solving for Z will give us 1.3

Then, we check this in the z table which will give us p = 0.9032

Therefore, the service level is 90.32%.