Discover the best answers at Westonci.ca, where experts share their insights and knowledge with you. Get detailed and precise answers to your questions from a dedicated community of experts on our Q&A platform. Join our Q&A platform to connect with experts dedicated to providing accurate answers to your questions in various fields.
Sagot :
Answer:
Total power cost= 1,250 + 1.375 * number of machine hours
Explanation:
Giving the following information:
Quarter Machine Hours Power Cost
1 20,000 $26,000
2 25,000 $38,000
3 30,000 $42,500
4 22,000 $37,000
5 21,000 $34,000
6 18,000 $29,000
7 24,000 $36,000
8 28,000 $40,000
To calculate the variable and fixed costs, we need to use the following formula:
Variable cost per unit= (Highest activity cost - Lowest activity cost)/ (Highest activity units - Lowest activity units)
Variable cost per unit= (42,500 - 26,000) - (30,000 - 18,000)
Variable cost per unit= $1.375
Fixed costs= Highest activity cost - (Variable cost per unit * HAU)
Fixed costs= 42,500 - (1.375*30,000)
Fixed costs= 1,250
Fixed costs= LAC - (Variable cost per unit* LAU)
Fixed costs= 26,000 - (1.375*18,000)
Fixed costs= 1,250
Thank you for trusting us with your questions. We're here to help you find accurate answers quickly and efficiently. Thank you for your visit. We're committed to providing you with the best information available. Return anytime for more. Get the answers you need at Westonci.ca. Stay informed with our latest expert advice.