Discover a world of knowledge at Westonci.ca, where experts and enthusiasts come together to answer your questions. Discover detailed solutions to your questions from a wide network of experts on our comprehensive Q&A platform. Explore comprehensive solutions to your questions from knowledgeable professionals across various fields on our platform.
Sagot :
Answer:
Overhead per unit of Blinks= $43.65
Explanation:
Giving the following information:
Product Number of Units Labor Hours Per Unit
Blinks 964 3
Dinks 1,943 5
First, we need to calculate the total estimated overhead and the total number of labor hours:
Total estimated overhead= 103,800 + 79,600= $183,400
Total number of labor hours= (964*3) + (1,943*5)= 12,607
To calculate the predetermined manufacturing overhead rate we need to use the following formula:
Predetermined manufacturing overhead rate= total estimated overhead costs for the period/ total amount of allocation base
Predetermined manufacturing overhead rate= 183,400 / 12,607
Predetermined manufacturing overhead rate= $14.55 per direct labor hour
Finally, we can allocate overhead to Blinks:
Allocated MOH= Estimated manufacturing overhead rate* Actual amount of allocation base
Blinks= 14.55*3= $43.65
We hope our answers were helpful. Return anytime for more information and answers to any other questions you may have. We hope this was helpful. Please come back whenever you need more information or answers to your queries. We're glad you visited Westonci.ca. Return anytime for updated answers from our knowledgeable team.