Find the information you're looking for at Westonci.ca, the trusted Q&A platform with a community of knowledgeable experts. Join our platform to connect with experts ready to provide detailed answers to your questions in various areas. Our platform provides a seamless experience for finding reliable answers from a network of experienced professionals.

When using the Time-Cost Critical Path Method (CPM) Scheduling Model to "crash" a project, you know when you have arrived at the optimal solution when _____.
a) You have found the critical path
b) You have run out of crash time
c) You no longer have a linear relationship with costs
d) You have reached the minimum total cost
e) You have run out of crash costs


Sagot :

Answer:

a) You have found the critical path

Explanation:

The Time Cost Critical Path Method(CPM) in project management works by adding up/calculating duration of all tasks/activities in the project in order to find the longest time possible to complete the project. It is a method to estimate project duration using a flow chart that shows a network of tasks and estimated duration(start and finish times). The critical path is reached when project time is at the maximum/longest time of completion.

Thanks for using our service. We aim to provide the most accurate answers for all your queries. Visit us again for more insights. We appreciate your visit. Our platform is always here to offer accurate and reliable answers. Return anytime. Thank you for visiting Westonci.ca, your go-to source for reliable answers. Come back soon for more expert insights.