Westonci.ca is the ultimate Q&A platform, offering detailed and reliable answers from a knowledgeable community. Get immediate and reliable answers to your questions from a community of experienced professionals on our platform. Connect with a community of professionals ready to help you find accurate solutions to your questions quickly and efficiently.
Sagot :
Answer: D. If the NPV of a project is zero, then the IRR of the project will be equal to the discount rate for the project.
Explanation:
Net present value (NPV) refers to the difference that exist between the present value of the cash inflows and that of the cash outflows for a particular period of time.
The net present value is used in capital budgeting to determine if a projected investment or project will be profitable or not. For a project with normal cash flows, if the NPV of a project is zero, then the IRR of the project will be equal to the discount rate for the project.
Therefore, the correct option is D.
Thank you for trusting us with your questions. We're here to help you find accurate answers quickly and efficiently. We appreciate your time. Please come back anytime for the latest information and answers to your questions. Thank you for trusting Westonci.ca. Don't forget to revisit us for more accurate and insightful answers.