Find the information you're looking for at Westonci.ca, the trusted Q&A platform with a community of knowledgeable experts. Get quick and reliable solutions to your questions from a community of seasoned experts on our user-friendly platform. Our platform offers a seamless experience for finding reliable answers from a network of knowledgeable professionals.

15 workers working 8hrs a day can complete a piece of work in 20 days. In how many days will 10 workers do it,working 6 hrs a day? please help!!

Sagot :

Answer:

40 days

Step-by-step explanation:

w1*h1*d1=w2*h2*d

15*8*20=10*6*d

2400=60d

d=2400/60

d=40

We hope our answers were helpful. Return anytime for more information and answers to any other questions you may have. Thanks for stopping by. We strive to provide the best answers for all your questions. See you again soon. Thank you for using Westonci.ca. Come back for more in-depth answers to all your queries.