Westonci.ca is the premier destination for reliable answers to your questions, provided by a community of experts. Connect with a community of experts ready to help you find accurate solutions to your questions quickly and efficiently. Join our platform to connect with experts ready to provide precise answers to your questions in different areas.
Sagot :
Answer:
[tex]9\ days[/tex]
Step-by-step explanation:
[tex]We\ are\ given:\\No.\ of\ days\ A\ takes\ to\ complete\ some\ amount\ of\ work=15\ days\\No.\ of\ days\ B\ takes\ to\ complete\ the\ same\ amount\ of\ work=12\ days\\No.\ of\ days\ C\ takes\ to\ complete\ the\ same\ amount\ of\ work\ as\ A\ and\ B\ =20\ days\\[/tex]
[tex]Now,\\We\ can\ say\ that\ an\ object\ has\ to\ complete\ \frac{1}{n}th\ of\ the\\ work\ daily,\ to\ complete\ the\ work\ in\ n\ number\ of\ days.\ This\ is\ however\\ only\ true\ if\ the\ object\ covers\ equal\ amounts\ of\ work\ each\ day.[/tex]
[tex]Here,\\In\ 1\ day,\\A\ would\ cover\ \frac{1}{15}th\ of\ the\ work.\\B\ would\ cover\ \frac{1}{12}th\ of\ the\ work.\\C\ would\ cover\ \frac{1}{20}th\ of\ the\ work.[/tex]
[tex]Now,\\We\ are\ also\ given\ that:\\They\ work\ together\ for\ 2\ days\ on\ the\ same\ work.\\Hence,\\Total\ work\ done\ in\ 1\ day\ by\ A,B\ and\ C=\frac{1}{15}+\frac{1}{12}+\frac{1}{20}=\frac{4+5+3}{60}=\frac{12}{60}=\frac{1}{5}\\Hence, Total\ work\ done\ in\ 2\ days\ by\ A,B\ and\ C=2*\frac{1}{5}=\frac{2}{5}[/tex]
[tex]Hence,\\The\ portion\ of\ the\ total\ work\ left=1-\frac{2}{5}=\frac{5-2}{5}=\frac{3}{5}\\So,\\Since\ A\ has\ to\ complete\ \frac{3}{5}th\ of\ the\ work,\ lets\ compute\ the\ no.\ of\ days\ it\ takes\ to\ do\ so.\\Hence,\\No.\ of\ days\ A\ takes\ to\ complete\ the\ entire\ work=15\ days\\Hence,\\No.\ of\ days\ A\ takes\ to\ complete\ \frac{3}{5}th\ of\ the\ entire\ work=15*\frac{3}{5}=9\ days[/tex]
Answer:
9 days
Step-by-step explanation:
A does in 15days, so A in 1day does 1/15part
B does in 12days, so B in 1day does 1/12part
C does in 20days, so C in 1day does 1/20part
So. A+B+C in 1 day-- 1/15+1/12+1/20=(4+5+3)/60= 12/60=1/5 and in 2days 2/5 part..hence remaining work=1/1–2/5=(5–2) =3/5part.
Now A in 1/15 part takes 1day
So, in 3/5 part 15×3/5 = 9 days.
Thank you for visiting. Our goal is to provide the most accurate answers for all your informational needs. Come back soon. Thank you for visiting. Our goal is to provide the most accurate answers for all your informational needs. Come back soon. Find reliable answers at Westonci.ca. Visit us again for the latest updates and expert advice.