Westonci.ca is the premier destination for reliable answers to your questions, provided by a community of experts. Connect with a community of experts ready to help you find accurate solutions to your questions quickly and efficiently. Join our platform to connect with experts ready to provide precise answers to your questions in different areas.

A can do a piece of work in 15 days. B can do the same work in 12 days and C can
finish the same piece of work in 20 days. They started the work together for 2 days
and then B and C leaves. In how many days will A finish the remaining work?​


Sagot :

Answer:

[tex]9\ days[/tex]

Step-by-step explanation:

[tex]We\ are\ given:\\No.\ of\ days\ A\ takes\ to\ complete\ some\ amount\ of\ work=15\ days\\No.\ of\ days\ B\ takes\ to\ complete\ the\ same\ amount\ of\ work=12\ days\\No.\ of\ days\ C\ takes\ to\ complete\ the\ same\ amount\ of\ work\ as\ A\ and\ B\ =20\ days\\[/tex]

[tex]Now,\\We\ can\ say\ that\ an\ object\ has\ to\ complete\ \frac{1}{n}th\ of\ the\\ work\ daily,\ to\ complete\ the\ work\ in\ n\ number\ of\ days.\ This\ is\ however\\ only\ true\ if\ the\ object\ covers\ equal\ amounts\ of\ work\ each\ day.[/tex]

[tex]Here,\\In\ 1\ day,\\A\ would\ cover\ \frac{1}{15}th\ of\ the\ work.\\B\ would\ cover\ \frac{1}{12}th\ of\ the\ work.\\C\ would\ cover\ \frac{1}{20}th\ of\ the\ work.[/tex]

[tex]Now,\\We\ are\ also\ given\ that:\\They\ work\ together\ for\ 2\ days\ on\ the\ same\ work.\\Hence,\\Total\ work\ done\ in\ 1\ day\ by\ A,B\ and\ C=\frac{1}{15}+\frac{1}{12}+\frac{1}{20}=\frac{4+5+3}{60}=\frac{12}{60}=\frac{1}{5}\\Hence, Total\ work\ done\ in\ 2\ days\ by\ A,B\ and\ C=2*\frac{1}{5}=\frac{2}{5}[/tex]

[tex]Hence,\\The\ portion\ of\ the\ total\ work\ left=1-\frac{2}{5}=\frac{5-2}{5}=\frac{3}{5}\\So,\\Since\ A\ has\ to\ complete\ \frac{3}{5}th\ of\ the\ work,\ lets\ compute\ the\ no.\ of\ days\ it\ takes\ to\ do\ so.\\Hence,\\No.\ of\ days\ A\ takes\ to\ complete\ the\ entire\ work=15\ days\\Hence,\\No.\ of\ days\ A\ takes\ to\ complete\ \frac{3}{5}th\ of\ the\ entire\ work=15*\frac{3}{5}=9\ days[/tex]

Answer:

9 days

Step-by-step explanation:

A does in 15days, so A in 1day does 1/15part

B does in 12days, so B in 1day does 1/12part

C does in 20days, so C in 1day does 1/20part

So. A+B+C in 1 day-- 1/15+1/12+1/20=(4+5+3)/60= 12/60=1/5 and in 2days 2/5 part..hence remaining work=1/1–2/5=(5–2) =3/5part.

Now A in 1/15 part takes 1day

So, in 3/5 part 15×3/5 = 9 days.

Thank you for visiting. Our goal is to provide the most accurate answers for all your informational needs. Come back soon. Thank you for visiting. Our goal is to provide the most accurate answers for all your informational needs. Come back soon. Find reliable answers at Westonci.ca. Visit us again for the latest updates and expert advice.