At Westonci.ca, we connect you with the answers you need, thanks to our active and informed community. Explore comprehensive solutions to your questions from knowledgeable professionals across various fields on our platform. Join our platform to connect with experts ready to provide precise answers to your questions in different areas.
Sagot :
Answer:
[tex]9\ days[/tex]
Step-by-step explanation:
[tex]We\ are\ given:\\No.\ of\ days\ A\ takes\ to\ complete\ some\ amount\ of\ work=15\ days\\No.\ of\ days\ B\ takes\ to\ complete\ the\ same\ amount\ of\ work=12\ days\\No.\ of\ days\ C\ takes\ to\ complete\ the\ same\ amount\ of\ work\ as\ A\ and\ B\ =20\ days\\[/tex]
[tex]Now,\\We\ can\ say\ that\ an\ object\ has\ to\ complete\ \frac{1}{n}th\ of\ the\\ work\ daily,\ to\ complete\ the\ work\ in\ n\ number\ of\ days.\ This\ is\ however\\ only\ true\ if\ the\ object\ covers\ equal\ amounts\ of\ work\ each\ day.[/tex]
[tex]Here,\\In\ 1\ day,\\A\ would\ cover\ \frac{1}{15}th\ of\ the\ work.\\B\ would\ cover\ \frac{1}{12}th\ of\ the\ work.\\C\ would\ cover\ \frac{1}{20}th\ of\ the\ work.[/tex]
[tex]Now,\\We\ are\ also\ given\ that:\\They\ work\ together\ for\ 2\ days\ on\ the\ same\ work.\\Hence,\\Total\ work\ done\ in\ 1\ day\ by\ A,B\ and\ C=\frac{1}{15}+\frac{1}{12}+\frac{1}{20}=\frac{4+5+3}{60}=\frac{12}{60}=\frac{1}{5}\\Hence, Total\ work\ done\ in\ 2\ days\ by\ A,B\ and\ C=2*\frac{1}{5}=\frac{2}{5}[/tex]
[tex]Hence,\\The\ portion\ of\ the\ total\ work\ left=1-\frac{2}{5}=\frac{5-2}{5}=\frac{3}{5}\\So,\\Since\ A\ has\ to\ complete\ \frac{3}{5}th\ of\ the\ work,\ lets\ compute\ the\ no.\ of\ days\ it\ takes\ to\ do\ so.\\Hence,\\No.\ of\ days\ A\ takes\ to\ complete\ the\ entire\ work=15\ days\\Hence,\\No.\ of\ days\ A\ takes\ to\ complete\ \frac{3}{5}th\ of\ the\ entire\ work=15*\frac{3}{5}=9\ days[/tex]
Answer:
9 days
Step-by-step explanation:
A does in 15days, so A in 1day does 1/15part
B does in 12days, so B in 1day does 1/12part
C does in 20days, so C in 1day does 1/20part
So. A+B+C in 1 day-- 1/15+1/12+1/20=(4+5+3)/60= 12/60=1/5 and in 2days 2/5 part..hence remaining work=1/1–2/5=(5–2) =3/5part.
Now A in 1/15 part takes 1day
So, in 3/5 part 15×3/5 = 9 days.
Thank you for visiting our platform. We hope you found the answers you were looking for. Come back anytime you need more information. Thank you for choosing our platform. We're dedicated to providing the best answers for all your questions. Visit us again. Find reliable answers at Westonci.ca. Visit us again for the latest updates and expert advice.