At Westonci.ca, we connect you with the answers you need, thanks to our active and informed community. Explore a wealth of knowledge from professionals across different disciplines on our comprehensive platform. Our platform offers a seamless experience for finding reliable answers from a network of knowledgeable professionals.
Sagot :
Answer:
[tex]9\ days[/tex]
Step-by-step explanation:
[tex]We\ are\ given:\\No.\ of\ days\ A\ takes\ to\ complete\ some\ amount\ of\ work=15\ days\\No.\ of\ days\ B\ takes\ to\ complete\ the\ same\ amount\ of\ work=12\ days\\No.\ of\ days\ C\ takes\ to\ complete\ the\ same\ amount\ of\ work\ as\ A\ and\ B\ =20\ days\\[/tex]
[tex]Now,\\We\ can\ say\ that\ an\ object\ has\ to\ complete\ \frac{1}{n}th\ of\ the\\ work\ daily,\ to\ complete\ the\ work\ in\ n\ number\ of\ days.\ This\ is\ however\\ only\ true\ if\ the\ object\ covers\ equal\ amounts\ of\ work\ each\ day.[/tex]
[tex]Here,\\In\ 1\ day,\\A\ would\ cover\ \frac{1}{15}th\ of\ the\ work.\\B\ would\ cover\ \frac{1}{12}th\ of\ the\ work.\\C\ would\ cover\ \frac{1}{20}th\ of\ the\ work.[/tex]
[tex]Now,\\We\ are\ also\ given\ that:\\They\ work\ together\ for\ 2\ days\ on\ the\ same\ work.\\Hence,\\Total\ work\ done\ in\ 1\ day\ by\ A,B\ and\ C=\frac{1}{15}+\frac{1}{12}+\frac{1}{20}=\frac{4+5+3}{60}=\frac{12}{60}=\frac{1}{5}\\Hence, Total\ work\ done\ in\ 2\ days\ by\ A,B\ and\ C=2*\frac{1}{5}=\frac{2}{5}[/tex]
[tex]Hence,\\The\ portion\ of\ the\ total\ work\ left=1-\frac{2}{5}=\frac{5-2}{5}=\frac{3}{5}\\So,\\Since\ A\ has\ to\ complete\ \frac{3}{5}th\ of\ the\ work,\ lets\ compute\ the\ no.\ of\ days\ it\ takes\ to\ do\ so.\\Hence,\\No.\ of\ days\ A\ takes\ to\ complete\ the\ entire\ work=15\ days\\Hence,\\No.\ of\ days\ A\ takes\ to\ complete\ \frac{3}{5}th\ of\ the\ entire\ work=15*\frac{3}{5}=9\ days[/tex]
Answer:
9 days
Step-by-step explanation:
A does in 15days, so A in 1day does 1/15part
B does in 12days, so B in 1day does 1/12part
C does in 20days, so C in 1day does 1/20part
So. A+B+C in 1 day-- 1/15+1/12+1/20=(4+5+3)/60= 12/60=1/5 and in 2days 2/5 part..hence remaining work=1/1–2/5=(5–2) =3/5part.
Now A in 1/15 part takes 1day
So, in 3/5 part 15×3/5 = 9 days.
Thank you for visiting. Our goal is to provide the most accurate answers for all your informational needs. Come back soon. Thanks for using our service. We're always here to provide accurate and up-to-date answers to all your queries. Find reliable answers at Westonci.ca. Visit us again for the latest updates and expert advice.