At Westonci.ca, we make it easy to get the answers you need from a community of informed and experienced contributors. Discover in-depth answers to your questions from a wide network of professionals on our user-friendly Q&A platform. Get detailed and accurate answers to your questions from a dedicated community of experts on our Q&A platform.
Sagot :
1. Direct cost is:
= $97,475
Training cost is:
= $18,150
Total cost of Management Information System is:
= $115,625
2. The number of years that the break-even of this project cost will be achieved is:
= 5 years.
Data and Calculations:
Cost of the MIS:
150 computers at $500 each, = $75,000 (150 x $500)
5 Printers at $400 each = 2,000 (5 x $400)
5 network connections at $900 each = 4,500 (5 x $900)
20 boxes of Papers and stationery at $50 each 1,000 (20 x $50)
5 Scanners at $2,995 each 14,975 (5 * $2,995)
Total direct costs of the new MIS = $97,475
The training costs:
Fringe benefits $50 each to 150 participants = $7,500 ($50 x 150)
15 trainers at $ 500 each. 7,500 ($500 x 15)
Training room cost $750 per session 2,250 ($750 x 3)
Administrative cost is $300 per session 900 ($300 x 3)
Total cost of training $18,150
Total cost of the Management Information System = $115,625 ($97,475 + $18,150)
Annual benefits = $25,000
Break-even project cost (payback period) will be achieved in 4.625 years ($115,625/$25,000)
= 5 years approximately
Learn more about Break-even period (payback period) here: https://brainly.com/question/13894900
Thanks for stopping by. We are committed to providing the best answers for all your questions. See you again soon. Thanks for using our service. We're always here to provide accurate and up-to-date answers to all your queries. Thank you for visiting Westonci.ca. Stay informed by coming back for more detailed answers.