At Westonci.ca, we make it easy to get the answers you need from a community of informed and experienced contributors. Discover in-depth answers to your questions from a wide network of professionals on our user-friendly Q&A platform. Get detailed and accurate answers to your questions from a dedicated community of experts on our Q&A platform.

Blooming Sun investment corporation is facing problems in their records
maintenance, So they have decided to launch a new Management Information
system. The cost of MIS includes 150 computers at $500 each, 5 Printers at
$400 each, 5 network connections at $900 each, 20 boxes of Papers and
stationery at $50 each, 5 Scanners at $2995 each. The training cost that is
required to be provided to the staff includes fringe benefits $50 each to 150
participants, 15 trainers at $ 500 each. Training room is required for three
sessions which will cost $750 per session and administrative cost is $300 per
session.
The experts have estimated that the new MIS will be helpful in adding $25000
per year in benefits.
Questions:
1. Identify the direct cost, Training cost and total cost of Management information system?

2. In how many years the breakeven of this project cost will be achieved?


Sagot :

Answer:

Achived that the breakeven

1. Direct cost is:

= $97,475

Training cost is:

= $18,150

Total cost of Management Information System is:

= $115,625

2. The number of years that the break-even of this project cost will be achieved is:

= 5 years.

Data and Calculations:

Cost of the MIS:

150 computers at $500 each, =                         $75,000 (150 x $500)

5 Printers at  $400 each =                                       2,000 (5 x $400)

5 network connections at $900 each =                4,500 (5 x $900)

20 boxes of Papers and  stationery at $50 each  1,000 (20 x $50)

5 Scanners at $2,995 each                                 14,975 (5 * $2,995)

Total direct costs of the new MIS =                  $97,475

The training costs:

Fringe benefits $50 each to 150  participants = $7,500 ($50 x 150)

15 trainers at $ 500 each.                                     7,500 ($500 x 15)

Training room cost $750 per session                 2,250 ($750 x 3)

Administrative cost is $300 per  session                900 ($300 x 3)

Total cost of training                                          $18,150

Total cost of the Management Information System = $115,625 ($97,475 + $18,150)

Annual benefits = $25,000

Break-even project cost (payback period) will be achieved in 4.625 years ($115,625/$25,000)

= 5 years approximately

Learn more about Break-even period (payback period) here: https://brainly.com/question/13894900

Thanks for stopping by. We are committed to providing the best answers for all your questions. See you again soon. Thanks for using our service. We're always here to provide accurate and up-to-date answers to all your queries. Thank you for visiting Westonci.ca. Stay informed by coming back for more detailed answers.