Westonci.ca connects you with experts who provide insightful answers to your questions. Join us today and start learning! Join our platform to connect with experts ready to provide precise answers to your questions in various areas. Connect with a community of professionals ready to help you find accurate solutions to your questions quickly and efficiently.

See the answer
1. Green Construction Co. has consistently used the percentage-of-completion method of recognizing revenue. During 2014, Green entered into a fixed-price contract to construct an office building for $24,000,000. Information relating to the contract is as follows:

At December 31

2014 2015

Percentage of completion 15% 45%

Estimated total cost at completion $18,000,000 $19,200,000

Gross profit recognized (cumulative) 1,200,000 2,880,000

Contract costs incurred during 2015 were ??

1. Green Construction Co. has consistently used the percentage-of-completion method of recognizing revenue. During 2014, Green entered into a fixed-price contract to construct an office building for $24,000,000. Information relating to the contract is as follows:

At December 31

2014 2015

Percentage of completion 15% 45%

Estimated total cost at completion $18,000,000 $19,200,000

Gross profit recognized (cumulative) 1,200,000 2,880,000

Contract costs incurred during 2015 were

a. $5,760,000.

b. $5,940,000.

c. $6,300,000.

d. $8,640,000.