Welcome to Westonci.ca, your one-stop destination for finding answers to all your questions. Join our expert community now! Explore thousands of questions and answers from knowledgeable experts in various fields on our Q&A platform. Connect with a community of professionals ready to help you find accurate solutions to your questions quickly and efficiently.

The bottom-up method of estimating where work package time and costs for past projects are used as a starting point for a new project and adjustments are made based on differences in the new project is known as the ___________.
a. range estimating.
b. phase estimating method.
c. WBS method.
d. template method.
e. parametric procedure.