Westonci.ca connects you with experts who provide insightful answers to your questions. Join us today and start learning! Discover comprehensive solutions to your questions from a wide network of experts on our user-friendly platform. Explore comprehensive solutions to your questions from a wide range of professionals on our user-friendly platform.
Sagot :
Answer:
- 10 men
Step-by-step explanation:
Amount of work done by 15 men is:
- 15 men *25 day = 15*25 man*days
Same work can be done by 25 men, in 15 days, so 10 more men should be added.
Thanks for using our service. We're always here to provide accurate and up-to-date answers to all your queries. We hope you found what you were looking for. Feel free to revisit us for more answers and updated information. Westonci.ca is committed to providing accurate answers. Come back soon for more trustworthy information.