Welcome to Westonci.ca, where curiosity meets expertise. Ask any question and receive fast, accurate answers from our knowledgeable community. Get immediate and reliable answers to your questions from a community of experienced professionals on our platform. Get precise and detailed answers to your questions from a knowledgeable community of experts on our Q&A platform.

8 students take 18 hours to construct a raft.
If the raft needs to be completed 12 hours earlier, calculate how many more students are needed.

Sagot :

Answer:

16

Step-by-step explanation:

Students                      8       x

Time taken (hours)     18     18 - 12 = 6

If number of students increases, the work will completed in less hours.

So inverse proportion

[tex]x =\frac{18*8}{6}=3*8 = 24[/tex]

Additional students required = 24 - 8 = 16