Discover the answers you need at Westonci.ca, a dynamic Q&A platform where knowledge is shared freely by a community of experts. Explore a wealth of knowledge from professionals across various disciplines on our comprehensive Q&A platform. Discover detailed answers to your questions from a wide network of experts on our comprehensive Q&A platform.

A can do a piece of work in 3 days and B in 6 days andShyam in 12 days.In how many days will they finish it when both work at it.​

Sagot :

Answer:

Step-by-step explanation:

= 1/3 + 1/6 + 1/12 (LCM 12)

= 4/12 + 2/6 + 1/12

= 6/12

= 1/2

Therefore 1/2 = 2 days

They will all work together and finish the job in 2 days