Discover the answers you need at Westonci.ca, where experts provide clear and concise information on various topics. Get quick and reliable solutions to your questions from a community of experienced experts on our platform. Discover in-depth answers to your questions from a wide network of professionals on our user-friendly Q&A platform.

A can do a piece of work in 3 days and B in 6 days. In how many days will they do it together? ​

Sagot :

Answer: 2 days

Step-by-step explanation:

We will add there work together

= 1/3 + 1/6

= 2/6 + 1/6 (LCM 6)

= 3/6

= 1/2

Therefore 1/2 = 2 days

Therefore it will take them 2 days