Welcome to Westonci.ca, your go-to destination for finding answers to all your questions. Join our expert community today! Explore a wealth of knowledge from professionals across various disciplines on our comprehensive Q&A platform. Get precise and detailed answers to your questions from a knowledgeable community of experts on our Q&A platform.

1 by 6 of a construction work is finished in the first year, 1 by 8 part in the second year and 1 by 12 in the third year how much work is finished in 3 year

Sagot :

Answer:

3/8

Step-by-step explanation:

first year's work is 1/6

second year's work is 1/8

third year's work is 1/12

combining all 3 gives us

1/6 + 1/8 + 1/12

which simplifies to 3/8

Thank you for your visit. We're committed to providing you with the best information available. Return anytime for more. We hope you found this helpful. Feel free to come back anytime for more accurate answers and updated information. Westonci.ca is your go-to source for reliable answers. Return soon for more expert insights.