At Westonci.ca, we connect you with experts who provide detailed answers to your most pressing questions. Start exploring now! Experience the convenience of finding accurate answers to your questions from knowledgeable professionals on our platform. Get detailed and accurate answers to your questions from a dedicated community of experts on our Q&A platform.

You are the financial manager of the Crossrail 1 project in London. The Board overseeing the project, acting on behalf of the UK Government, has asked you to provide a financial analysis of the project for business planning purposes. With two years to go before the commencement of train operations, you have assembled the most recent estimates of the capital investment cost and net revenues, which were forecast 1 year ago. While the user benefits and ticket revenues are assumed to remain the same each year of the 60-year useful life, it is anticipated that maintenance costs will be higher in the final 30 years of the project. They are shown in Table.
Item of cash flow Today Each year (for the first Each year (for years
(£bn) 30 years) (£bn) 31 to 60) (£bn)
Capital investment -9.4
User benefits (Includes
Time savings, Traffic
congestion relief) 0.843 0.843
Ticket revenues 0.3 0.3
Operational costs and maintenance -0.422 -0.609
For projects such as Crossrail 1, the UK Government typically estimates a 60-year useful life and uses a discount rate of 3.5%.
a) What is the net present value (NPV) of the project?
a. "£15.04".
b. "£8.83".
c. "£7.36".
d. "£16.76".
b) What is the payback period of the project?
a. "13.04".
b. "8.22".
c. "17.60".
d. "7.49".
c) What is the internal rate of return (IRR) of the project?
a. "7.57%".
b. "7.35%".
c. "5.44%".
d. "6.52%".
d) Based on your calculations is Crossrail 1 a viable project at the discount rate?
a. "Yes".
b. "No".
You have been asked by the Board to present an analysis that incorporates more recent cash flow information about the Crossrail 1 project. Before the project becomes operational, the capital investment has been given a worse scenario estimate that is 35% above the forecast in table 1. The Board would like to see the analysis if the net cash inflows will also be 35% below expectation over the 60-year life whether under the existing hurdle rate of 3.5% it would remain viable.
a) What is the net present value (NPV) of the project?
a. "-£2.16".
b. "£4.78".
c. "£3.20".
d. "-£1.80".
b) What is the internal rate of return (IRR) of the project?
a. "2.72%".
b. "3.10%".
c. "1.79%".
d/ "0.67%".
c) Based on your calculations is Crossrail 1 a viable project at the discount rate?
a. "Yes".
b. "No".


Sagot :

Crossrail 1 project is about to start in London.

This project will require an initial investment of 9.4 billion. The project will start earning cash flows from year  and it will continue to year 60 which is useful life of the project.

The NPV for the project will be 7.36 which is positive. The correct answer is c.

The payback period for project is 13.04 years which is given in the option a so correct answer is a.

The internal rate of return for the project is b. 7.35 .

Based on our analytics and calculation since NPV is positive so cross rail project is beneficial. The board should consider launching this project.

Learn more at  https://brainly.com/question/24353321