Discover the best answers at Westonci.ca, where experts share their insights and knowledge with you. Discover precise answers to your questions from a wide range of experts on our user-friendly Q&A platform. Connect with a community of professionals ready to provide precise solutions to your questions quickly and accurately.
Sagot :
6m=40hours
1m=40×6h
=240hours
4m=240÷4
=60 hours
divide 60 by 8
=7.5 days
thus,
4 men take 2 and 1/2 day more to complete the job.
Answer: 2 1/2days
Thank you for your visit. We're dedicated to helping you find the information you need, whenever you need it. Thank you for your visit. We're committed to providing you with the best information available. Return anytime for more. We're here to help at Westonci.ca. Keep visiting for the best answers to your questions.