Westonci.ca is your go-to source for answers, with a community ready to provide accurate and timely information. Experience the convenience of getting reliable answers to your questions from a vast network of knowledgeable experts. Our platform offers a seamless experience for finding reliable answers from a network of knowledgeable professionals.

Six men working 8 hours a day dig a shamba in 5 days. How many more days will it take 4 men working 8 hours a day to finish the job?
NOTE:PLEASE EXPLAIN IN DETAIL !!!


Sagot :

6m=40hours

1m=40×6h

=240hours

4m=240÷4

=60 hours

divide 60 by 8

=7.5 days

thus,

4 men take 2 and 1/2 day more to complete the job.

Answer: 2 1/2days

Thank you for visiting. Our goal is to provide the most accurate answers for all your informational needs. Come back soon. We hope our answers were useful. Return anytime for more information and answers to any other questions you have. Thank you for using Westonci.ca. Come back for more in-depth answers to all your queries.