Westonci.ca connects you with experts who provide insightful answers to your questions. Join us today and start learning! Ask your questions and receive detailed answers from professionals with extensive experience in various fields. Discover detailed answers to your questions from a wide network of experts on our comprehensive Q&A platform.

A and B can do a work in 3 days but A working alone takes 4 days. In what time will B do it if he works alone?

Could you help me. I'll give a heart and a brainliest to the one who helps me. If they write any nonsense, I will report them ;)


Sagot :

Answer:

Let B have x days work:

A + B = 3 days

1/4 + 1/x = 1/3

1/3 - 1/4 = 1/x

1/12 = 1/x

x = 1 / (1/12)

x = 12

B takes 12 days