Welcome to Westonci.ca, where finding answers to your questions is made simple by our community of experts. Get quick and reliable solutions to your questions from a community of experienced experts on our platform. Get quick and reliable solutions to your questions from a community of experienced experts on our platform.

32 workers can complete a work in 30 days working 6 hours per day. How many days are required to complete the
same work by 16 workers working 8 hours per day?


Sagot :

Tasyha

Answer:

45 days

Step-by-step explanation:

[tex]32 \times 30 \times 6 \div (16 \times 8) [/tex]

[tex]5760 \div 128[/tex]

[tex]\boxed{\green{ = 45}}[/tex]