Discover the answers you need at Westonci.ca, a dynamic Q&A platform where knowledge is shared freely by a community of experts. Get quick and reliable solutions to your questions from knowledgeable professionals on our comprehensive Q&A platform. Experience the convenience of finding accurate answers to your questions from knowledgeable experts on our platform.

A firm is deciding whether or not to complete the building of a new office.
Given the following data, what is the relevant cost of building an office building?
1. $10 million has been spent to date.
II. The partially completed building and land can be sold for $4 million.
III. Additional labor and material necessary to complete the office building costs $5 million.


Sagot :

The relevant cost of building an office building is $9 million.

  • The calculation of the relevant cost of building an office building is as follows:

= Sale value of partially completed building and land + additional labor & material required

= $4 million + $5 million

= $9 million

Therefore we can conclude that the relevant cost of building an office building is $9 million.