Explore Westonci.ca, the leading Q&A site where experts provide accurate and helpful answers to all your questions. Explore thousands of questions and answers from a knowledgeable community of experts on our user-friendly platform. Explore comprehensive solutions to your questions from a wide range of professionals on our user-friendly platform.

A can do a work in 35 days while B can do the same work in 140 days. What percentage of the work will be done in 14 days if they work together?

Sagot :

Answer:

½

Step-by-step explanation:

Amount of work A can do in a day: 1/35

Amount of work B can do in a day: 1/140

Amount of work A can do in 14 days: 1/35×14=⅖

Amount of work B can do in 14 days: 1/140x14=1/10

Total amount of work done in 14 days= ⅖+1/10=½

Thanks for using our service. We aim to provide the most accurate answers for all your queries. Visit us again for more insights. Thanks for stopping by. We strive to provide the best answers for all your questions. See you again soon. Your questions are important to us at Westonci.ca. Visit again for expert answers and reliable information.