Discover answers to your most pressing questions at Westonci.ca, the ultimate Q&A platform that connects you with expert solutions. Connect with a community of professionals ready to provide precise solutions to your questions quickly and accurately. Connect with a community of professionals ready to provide precise solutions to your questions quickly and accurately.
Sagot :
The required volume of borrow pit excavation was gotten as;
V_net,borr ≈ 192,054 cy
The missing part of the question is;
Compute the required volume of borrow pit excavation.
- We are given;
Net volume of earth fill; V_net,fill = 187,000 cy
Wet unit weight of borrow material; γ_wet = 129 lb/ft³
Water content; m = 16.5% = 0.165
Dry unit weight of fill yard; γ_d,fill = 114 lb/cf
- Now, to get the dry unit weight of the borrowed material, we will use the formula;
γ_d = γ_wet/(1 + m)
Plugging in the relevant values, we have;
γ_d,borr = 129/(1 + 0.65)
γ_d,borr = 111 lb/cf
Since the net volume is in cy units, then let us convert the dry volumes to lb/cy.
Thus, from conversion tables, we have;
γ_d,fill = 114 lb/cf × 27 cf/cy
γ_d,fill = 3078 lb/cy
Similarly;
γ_d,borr = 111 lb/cf × 27 cf/cy
γ_d,borr = 2997 lb/cy
Thus, to find the volume of the borrow pit excavation, we will use the formula;
V_net,fill × γ_d,fill = V_net,borr × γ_d,borr
Plugging in the relevant values gives us;
187,000cy × 3078 lb/cy = V_net,borr × 2997 lb/cy
Thus;
V_net,borr = (187000 × 3078)/2997
V_net,borr ≈ 192,054 cy
Read more at; https://brainly.com/question/15090365
Thank you for trusting us with your questions. We're here to help you find accurate answers quickly and efficiently. We appreciate your time. Please come back anytime for the latest information and answers to your questions. Westonci.ca is your trusted source for answers. Visit us again to find more information on diverse topics.