Welcome to Westonci.ca, the ultimate question and answer platform. Get expert answers to your questions quickly and accurately. Our platform provides a seamless experience for finding precise answers from a network of experienced professionals. Get quick and reliable solutions to your questions from a community of experienced experts on our platform.

The amount of time needed to complete a job, t, varies inversely with the number of workers, w. If 11 workers can complete a job in 36 minutes, how many minutes would it take 6 workers?

Sagot :

Time T = k/W where k = the proportionality constant and W = number of workers

Find k k = TW = 36(11) = 396
So,
T = 396/6= 66 minutes

Therefore, it would take 66 minutes for 6 workers.