Get the answers you need at Westonci.ca, where our expert community is dedicated to providing you with accurate information. Join our Q&A platform to connect with experts dedicated to providing accurate answers to your questions in various fields. Connect with a community of professionals ready to provide precise solutions to your questions quickly and accurately.

The amount of time needed to complete a job, t, varies inversely with the number of workers, w. If 11 workers can complete a job in 36 minutes, how many minutes would it take 6 workers?

Sagot :

Time T = k/W where k = the proportionality constant and W = number of workers

Find k k = TW = 36(11) = 396
So,
T = 396/6= 66 minutes

Therefore, it would take 66 minutes for 6 workers.