Find the best answers to your questions at Westonci.ca, where experts and enthusiasts provide accurate, reliable information. Join our Q&A platform to connect with experts dedicated to providing precise answers to your questions in different areas. Join our Q&A platform to connect with experts dedicated to providing accurate answers to your questions in various fields.

if 40 workers can complete a piece of work in 15 days how many workers should be employed to complete the same work in 3 days​

Sagot :

8 workers. 15/3=5. 40/5=8