Looking for answers? Westonci.ca is your go-to Q&A platform, offering quick, trustworthy responses from a community of experts. Get quick and reliable solutions to your questions from a community of seasoned experts on our user-friendly platform. Discover in-depth answers to your questions from a wide network of professionals on our user-friendly Q&A platform.
Sagot :
Person 1: They can sort the mail in 30 minutes, so they do 1/30th of the job in one minute.
Person 2: They can sort the mail in 45 minutes, so they do 1/45th of the job in one minute.
Person 3: They can sort the mail in 90 minutes, so they do 1/90th of the job in one minute.
Together, they do (1/30 + 1/45 + 1/90)th of the job in one minute.
1/30 + 1/45 + 1/90 = 3/90 + 2/90 + 1/90 = 6/90
So they do 6/90 of the job together in 1 minute.
If "t" is the time it takes them working together to do the job, then we need to solve
6/90 · t = 1 (that's 1 for 1 whole job)
Solving that, you get t = 90/6 = 15
So, it'd take them 15 minutes working together to get that job done.
Thank you for your visit. We're committed to providing you with the best information available. Return anytime for more. Thank you for your visit. We're committed to providing you with the best information available. Return anytime for more. We're glad you chose Westonci.ca. Revisit us for updated answers from our knowledgeable team.