Westonci.ca is your go-to source for answers, with a community ready to provide accurate and timely information. Our platform provides a seamless experience for finding precise answers from a network of experienced professionals. Get precise and detailed answers to your questions from a knowledgeable community of experts on our Q&A platform.

Roget Factory has budgeted factory overhead for the year at $4,640,000. It plans to produce 2,000,000 units of product. Budgeted direct labor hours are 320,000, and budgeted machine hours are 750,000. Using a single plantwide factory overhead rate based on direct labor hours, the factory overhead rate for the year is

Sagot :

Answer:

$15.4