Welcome to Westonci.ca, where finding answers to your questions is made simple by our community of experts. Join our Q&A platform and connect with professionals ready to provide precise answers to your questions in various areas. Join our Q&A platform to connect with experts dedicated to providing accurate answers to your questions in various fields.

Jin schedules 496 hours for a project. He plans to work 8 hours each day. How many days will it take to complete the project?​

Sagot :

Answer:

62 days

Step-by-step explanation:

496/8 = 62

496/8=62