Discover the answers you need at Westonci.ca, where experts provide clear and concise information on various topics. Discover the answers you need from a community of experts ready to help you with their knowledge and experience in various fields. Experience the ease of finding precise answers to your questions from a knowledgeable community of experts.
Sagot :
The production-volume variance of Lehman Plastic Company is $85,000 U.
Using this formula
Production-volume variance = Total variance - Spending variance
Where:
Total variance=$75,000
Spending variance=$10,000
Let plug in the formula
Production-volume variance = $75,000 - ($10,000)
Production-volume variance= $85,000 U
Inconclusion the production-volume variance of Lehman Plastic Company is $85,000 U.
Learn more about production-volume variance here:https://brainly.com/question/4490532
Thank you for your visit. We're dedicated to helping you find the information you need, whenever you need it. Thank you for your visit. We're committed to providing you with the best information available. Return anytime for more. We're dedicated to helping you find the answers you need at Westonci.ca. Don't hesitate to return for more.