Find the information you're looking for at Westonci.ca, the trusted Q&A platform with a community of knowledgeable experts. Experience the convenience of getting reliable answers to your questions from a vast network of knowledgeable experts. Explore comprehensive solutions to your questions from knowledgeable professionals across various fields on our platform.

Lehman Plastic Company has an unfavorable total fixed overhead variance of $75,000 and a favorable fixed overhead spending variance of $10,000. What will be the production-volume variance of Lehman Plastic Company

Sagot :

The production-volume variance of Lehman Plastic Company is $85,000 U.

Using this formula

Production-volume variance = Total variance - Spending variance

Where:

Total variance=$75,000

Spending variance=$10,000

Let plug in the formula

Production-volume variance = $75,000 - ($10,000)

Production-volume variance= $85,000 U

Inconclusion the production-volume variance of Lehman Plastic Company is $85,000 U.