Discover the answers you need at Westonci.ca, where experts provide clear and concise information on various topics. Discover the answers you need from a community of experts ready to help you with their knowledge and experience in various fields. Experience the ease of finding precise answers to your questions from a knowledgeable community of experts.

Lehman Plastic Company has an unfavorable total fixed overhead variance of $75,000 and a favorable fixed overhead spending variance of $10,000. What will be the production-volume variance of Lehman Plastic Company

Sagot :

The production-volume variance of Lehman Plastic Company is $85,000 U.

Using this formula

Production-volume variance = Total variance - Spending variance

Where:

Total variance=$75,000

Spending variance=$10,000

Let plug in the formula

Production-volume variance = $75,000 - ($10,000)

Production-volume variance= $85,000 U

Inconclusion the production-volume variance of Lehman Plastic Company is $85,000 U.

Learn more about production-volume variance here:https://brainly.com/question/4490532

Thank you for your visit. We're dedicated to helping you find the information you need, whenever you need it. Thank you for your visit. We're committed to providing you with the best information available. Return anytime for more. We're dedicated to helping you find the answers you need at Westonci.ca. Don't hesitate to return for more.