Explore Westonci.ca, the leading Q&A site where experts provide accurate and helpful answers to all your questions. Connect with a community of professionals ready to provide precise solutions to your questions quickly and accurately. Discover in-depth answers to your questions from a wide network of professionals on our user-friendly Q&A platform.

To get detailed values of project schedule and cost performance, look at _____ and _____.

Sagot :

We need to look at the schedule variances and cost variances to get a detailed values of the project schedule and cost performance.

Basically, a project schedule helps to show what to be done, what to utilize and when the project is due.

  • The cost performance does show the financial effectiveness and efficiency of the project.

In conclusion, we definitely need to look at the schedule variances and cost variances to get a detailed values of the project schedule and cost performance.

Read more about schedule variances