Discover a wealth of knowledge at Westonci.ca, where experts provide answers to your most pressing questions. Discover the answers you need from a community of experts ready to help you with their knowledge and experience in various fields. Experience the convenience of finding accurate answers to your questions from knowledgeable experts on our platform.

You are part of the team assigned to implement new software at XYZ Inc. The employees at XYZ Inc. trust the results obtained from the old software, but are cautious about accepting those from the proposed new software. What software implementation strategy would you recommend in this situation to allow users fall-back access to the old system as the new one is implemented

Sagot :

There are different kinds of software implementation strategy. The software implementation strategy would you recommend in this situation to allow users fall-back access to the old system as the new one is implemented is parallel start up.

  • Parallel running often called parallel start up strategy for system changeover where a new system slowly takes over the roles of the older system even when both systems operate.

This conversion often occur when the technology of the old system is outdated and as such a new system is needed to be installed to replace the old one.

The parallel running phase is the act of changing a fragment of business information technology operation to a new system.

Learn more about Parallel start up from