Welcome to Westonci.ca, your ultimate destination for finding answers to a wide range of questions from experts. Get quick and reliable solutions to your questions from a community of seasoned experts on our user-friendly platform. Explore comprehensive solutions to your questions from knowledgeable professionals across various fields on our platform.
Sagot :
Answer:
6 days
Step-by-step explanation:
1 boy workload = 1/2 1 man workload
2 boys workload = 1/2*2 = 1 man workload
so 3 men + 2 boys workload = 4 men workload
3 men ..... 8 days ... 24man-days to build
4 men ..... x days ... 24man-days to build
x=24/4=6
We appreciate your time. Please come back anytime for the latest information and answers to your questions. We hope you found this helpful. Feel free to come back anytime for more accurate answers and updated information. Thank you for using Westonci.ca. Come back for more in-depth answers to all your queries.