Westonci.ca is the Q&A platform that connects you with experts who provide accurate and detailed answers. Experience the ease of finding quick and accurate answers to your questions from professionals on our platform. Experience the convenience of finding accurate answers to your questions from knowledgeable experts on our platform.
Sagot :
Answer:
6 days
Step-by-step explanation:
1 boy workload = 1/2 1 man workload
2 boys workload = 1/2*2 = 1 man workload
so 3 men + 2 boys workload = 4 men workload
3 men ..... 8 days ... 24man-days to build
4 men ..... x days ... 24man-days to build
x=24/4=6