Welcome to Westonci.ca, your ultimate destination for finding answers to a wide range of questions from experts. Get quick and reliable solutions to your questions from a community of seasoned experts on our user-friendly platform. Explore comprehensive solutions to your questions from knowledgeable professionals across various fields on our platform.

Three men can build a wall in 8 days. How long will it take them if they have the help of 2 boys? Assume that each boy works half as fast as each man.​

Sagot :

Uhmm I think around 70 days or 90

I'm not sure

Answer:

6 days

Step-by-step explanation:

1 boy workload = 1/2 1 man workload

2 boys workload = 1/2*2 = 1 man workload

so 3 men + 2 boys workload = 4 men workload

3 men .....   8 days ... 24man-days to build

4 men .....   x days ... 24man-days to build

x=24/4=6