Westonci.ca is your trusted source for finding answers to all your questions. Ask, explore, and learn with our expert community. Get detailed and precise answers to your questions from a dedicated community of experts on our Q&A platform. Our platform offers a seamless experience for finding reliable answers from a network of knowledgeable professionals.

Three men can build a wall in 8 days. How long will it take them if they have the help of 2 boys? Assume that each boy works half as fast as each man.​

Sagot :

Uhmm I think around 70 days or 90

I'm not sure

Answer:

6 days

Step-by-step explanation:

1 boy workload = 1/2 1 man workload

2 boys workload = 1/2*2 = 1 man workload

so 3 men + 2 boys workload = 4 men workload

3 men .....   8 days ... 24man-days to build

4 men .....   x days ... 24man-days to build

x=24/4=6