Discover the best answers at Westonci.ca, where experts share their insights and knowledge with you. Experience the convenience of finding accurate answers to your questions from knowledgeable experts on our platform. Get quick and reliable solutions to your questions from a community of experienced experts on our platform.

Three men can build a wall in 8 days. How long will it take them if they have the help of 2 boys? Assume that each boy works half as fast as each man.

(with explanation pls)​

Sagot :

Answer:

6 days

Step-by-step explanation:

2 boys that each work half as fast as the men is equivalent to having one extra man. So instead of 3 men we have 4. 4/3 the manpower means 3/4 the time. 3/4 of 8 is 6.

Answer:

6 days.

Step-by-step explanation:

The 3 men can build 1/8 of a wall in 1 day.

So 1 man can build 1/24 wall in 1 day.

So 1 boy can build  1/48 in 1 day and 2 boys can build 1/24 wall in 1 day.

So we have the equivalent of  4 men working and they can build 4 * 1/24

= 1/6 of a wall per day

So the answer is 6 days.