Westonci.ca is the premier destination for reliable answers to your questions, provided by a community of experts. Experience the convenience of finding accurate answers to your questions from knowledgeable experts on our platform. Discover in-depth answers to your questions from a wide network of professionals on our user-friendly Q&A platform.

Three men can build a wall in 8 days. How long will it take them if they have the help of 2 boys? Assume that each boy works half as fast as each man.

(with explanation pls)​


Sagot :

Answer:

6 days

Step-by-step explanation:

2 boys that each work half as fast as the men is equivalent to having one extra man. So instead of 3 men we have 4. 4/3 the manpower means 3/4 the time. 3/4 of 8 is 6.

Answer:

6 days.

Step-by-step explanation:

The 3 men can build 1/8 of a wall in 1 day.

So 1 man can build 1/24 wall in 1 day.

So 1 boy can build  1/48 in 1 day and 2 boys can build 1/24 wall in 1 day.

So we have the equivalent of  4 men working and they can build 4 * 1/24

= 1/6 of a wall per day

So the answer is 6 days.

Thank you for visiting our platform. We hope you found the answers you were looking for. Come back anytime you need more information. We appreciate your time. Please revisit us for more reliable answers to any questions you may have. Find reliable answers at Westonci.ca. Visit us again for the latest updates and expert advice.