Discover the best answers at Westonci.ca, where experts share their insights and knowledge with you. Experience the convenience of finding accurate answers to your questions from knowledgeable experts on our platform. Get quick and reliable solutions to your questions from a community of experienced experts on our platform.
Sagot :
Answer:
6 days
Step-by-step explanation:
2 boys that each work half as fast as the men is equivalent to having one extra man. So instead of 3 men we have 4. 4/3 the manpower means 3/4 the time. 3/4 of 8 is 6.
Answer:
6 days.
Step-by-step explanation:
The 3 men can build 1/8 of a wall in 1 day.
So 1 man can build 1/24 wall in 1 day.
So 1 boy can build 1/48 in 1 day and 2 boys can build 1/24 wall in 1 day.
So we have the equivalent of 4 men working and they can build 4 * 1/24
= 1/6 of a wall per day
So the answer is 6 days.
Thanks for using our platform. We're always here to provide accurate and up-to-date answers to all your queries. We hope this was helpful. Please come back whenever you need more information or answers to your queries. Discover more at Westonci.ca. Return for the latest expert answers and updates on various topics.