Westonci.ca offers quick and accurate answers to your questions. Join our community and get the insights you need today. Connect with a community of experts ready to provide precise solutions to your questions quickly and accurately. Get detailed and accurate answers to your questions from a dedicated community of experts on our Q&A platform.
Sagot :
Answer: A) 3
=========================================================
Explanation:
Let's say there are 216 machine parts that need to be made. I'm using this number since 12*18 = 216. Refer to the note at the bottom.
If person A works alone, then they can make those 216 parts in 12 days. Person A's unit rate is 216/12 = 18 parts per day.
Person B, working alone, has a rate of 216/18 = 12 parts per day.
If they work together without hindering one another, then their combined unit rate is 18+12 = 30 parts per day.
Working together for 6 days leads to 6*30 = 180 parts made so far. That leaves 216 - 180 = 36 parts left over for person B to finish up.
Since person B does so at a unit rate of 12 parts per day, this means person B needs 36/12 = 3 extra days.
--------------
Side note: There's nothing special about the value 216 I picked. I only selected that value so that dividing over 12 and 18 led to whole number results. You could pick the LCM of 12 and 18 to get the same idea.
We hope this information was helpful. Feel free to return anytime for more answers to your questions and concerns. Thank you for your visit. We're dedicated to helping you find the information you need, whenever you need it. Westonci.ca is here to provide the answers you seek. Return often for more expert solutions.